The road work continues on the campus.
The road is scheduled to be completed spring 2012.
No addtional updates at this time.
Wednesday, December 14, 2011
Monday, November 21, 2011
Thursday, October 13, 2011
Progress Update
Sent quote for cabling to facilities n the greenhouse.
Phase one road has begun construction.
Phase one road has begun construction.
Tuesday, October 4, 2011
Progress Update
The construction drawings are completed
Met with NE’s to review cabling path and communication for the greenhouse.
The new road construction has started for the project.
Met with NE’s to review cabling path and communication for the greenhouse.
The new road construction has started for the project.
Thursday, September 1, 2011
Thursday, August 25, 2011
Progress Update
As a part of phase one initial work on a new road will begin after Labor Day 2011.
The road will initially connect Middlebrook Road to the site of the Bioscience Education Center, creating a second entrance and exit to campus. Ultimately, the road will connect to Goldenrod Lane. This road is required by the county.
The road will initially connect Middlebrook Road to the site of the Bioscience Education Center, creating a second entrance and exit to campus. Ultimately, the road will connect to Goldenrod Lane. This road is required by the county.
Thursday, April 14, 2011
Progress Update
The architects is still working on the greenhouse design
Update project documentation and Blog.
Update project documentation and Blog.
Wednesday, March 30, 2011
Progress Update
Permit process continues with the state.
Update project documentation and Blog.
The greenhouse design continues to be worked on by the architects.
Update project documentation and Blog.
The greenhouse design continues to be worked on by the architects.
Thursday, February 10, 2011
Progress Update
Facilities working with architects on final design drawing.
Facilities is also working with vendors on all the permits.
Facilities is also working with vendors on all the permits.