The Greenhouse estimated cost for connectivity has been sent to facilities project manager.
The fiber connection appears to be the best solution for connectivity.
Thursday, December 9, 2010
Friday, November 19, 2010
Progress Update
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
On site visit with vendor to review the HT building layout for wireless point to point connection using an antenna.
The college NE group has decided that fiber to the new greenhouse is a good fit for connectivity.
Phase one bid is in the process of being reviewed by facilities.
On site visit with vendor to review the HT building layout for wireless point to point connection using an antenna.
The college NE group has decided that fiber to the new greenhouse is a good fit for connectivity.
Thursday, November 4, 2010
Progress Update
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
On site visit with vendor to review the HT building layout for wireless point to point connection using an antenna.
Phase one bid is in the process of being reviewed by facilities.
On site visit with vendor to review the HT building layout for wireless point to point connection using an antenna.
Friday, October 15, 2010
Progress Update
Meet with facilities and client to review their IT requirements.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
Sent facilities estimated quote for the IT equipment and labor for the greenhouse.A Scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity)
Sent facilities an estimated quote for infrastructure. The NE group is still working on other network design to lower the cost of data connectivity to the greenhouse.
Received server cabinet quote from Dell.
Confirm ABF tube size for GT vaults with the college NE’s.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
Sent facilities estimated quote for the IT equipment and labor for the greenhouse.A Scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity)
Sent facilities an estimated quote for infrastructure. The NE group is still working on other network design to lower the cost of data connectivity to the greenhouse.
Received server cabinet quote from Dell.
Confirm ABF tube size for GT vaults with the college NE’s.
Friday, October 1, 2010
Progress Update
Meet with facilities and client to review their IT requirements.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
Sent facilities estimated quote for the IT equipment and labor for the greenhouse.
A scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity
A meeting for GT BE Vault review has been setup for Oct 8th.
Sent facilities an estimated quote for infrastructure.
Follow up on a server cabinet quote from Dell.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
Sent facilities estimated quote for the IT equipment and labor for the greenhouse.
A scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity
A meeting for GT BE Vault review has been setup for Oct 8th.
Sent facilities an estimated quote for infrastructure.
Follow up on a server cabinet quote from Dell.
Tuesday, August 24, 2010
Progress Update
Following up with facilities to setup meeting with client to review their IT requirements.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one has been sent out for bid.
Follow up with facilities on the Greenhouse options for client.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one has been sent out for bid.
Follow up with facilities on the Greenhouse options for client.