Friday, October 15, 2010

Progress Update

Meet with facilities and client to review their IT requirements.
Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.
Sent facilities estimated quote for the IT equipment and labor for the greenhouse.A Scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity)
Sent facilities an estimated quote for infrastructure. The NE group is still working on other network design to lower the cost of data connectivity to the greenhouse.
Received server cabinet quote from Dell.
Confirm ABF tube size for GT vaults with the college NE’s.

Friday, October 1, 2010

Progress Update

Meet with facilities and client to review their IT requirements.

Phase one project estimated to start in October 2010 and be completed by Spring 2011
Phase one bid is in the process of being reviewed by facilities.

Sent facilities estimated quote for the IT equipment and labor for the greenhouse.

A scheduled walkthrough this Friday (Sept 24th with NE to determine which telecommunication closet to connect fiber to greenhouse for connectivity

A meeting for GT BE Vault review has been setup for Oct 8th.

Sent facilities an estimated quote for infrastructure.

Follow up on a server cabinet quote from Dell.